NPV Worked Example

This page works one economic feasibility case end to end: a small warehouse system, five years of cash flow, and the three numbers the approval committee asks for. The concepts behind it are in Feasibility Analysis.

The Scenario

A distributor wants to replace a manual stock-counting process with a warehouse tracking system.

  • Development cost, all in year 0: 180,000 (salaries, hardware, licences).
  • Operational cost, years 1 to 5: 30,000 a year (hosting, support, licence renewals), rising 5% a year with wages.
  • Tangible benefits, years 1 to 5: 90,000 in year 1 from reduced stock write-offs and fewer counting hours, growing 10% a year as more warehouses adopt it.
  • Discount rate: 8%, the rate the finance team uses for internal projects.

The benefit growth and cost inflation are assumptions, not facts. They are the first things to challenge in review, and the first things to revise when the numbers turn out wrong.

Step 1: Lay Out the Cash Flow

Year Costs Benefits Net cash flow Cumulative
0 180,000 0 −180,000 −180,000
1 30,000 90,000 60,000 −120,000
2 31,500 99,000 67,500 −52,500
3 33,075 108,900 75,825 23,325
4 34,729 119,790 85,061 108,386
5 36,465 131,769 95,304 203,690
Total 345,769 549,459 203,690

Step 2: Return on Investment

\[\mathrm{ROI} = \frac{\text{Total benefits} - \text{Total costs}}{\text{Total costs}} = \frac{549{,}459 - 345{,}769}{345{,}769} \approx 0.589\]

A 58.9% return over the five years. Note what this number cannot see: it treats the 180,000 spent in year 0 as equivalent to money spent in year 5.

Step 3: Break-Even Point

The cumulative column turns positive during year 3. Interpolating within that year:

\[\text{Break-even} = 2 + \frac{52{,}500}{75{,}825} \approx 2.69 \text{ years}\]

So the project pays for itself about eight months into year 3. This matters politically as much as financially: a break-even beyond the sponsor's planning horizon is a project that gets defunded halfway.

Step 4: Net Present Value

Each year's net cash flow is discounted at 8%:

\[\mathrm{NPV} = \sum_{t=0}^{5} \frac{B_t - C_t}{(1 + 0.08)^t}\]
Year Net cash flow Discount factor \(1/1.08^t\) Present value
0 −180,000 1.0000 −180,000
1 60,000 0.9259 55,556
2 67,500 0.8573 57,870
3 75,825 0.7938 60,193
4 85,061 0.7350 62,522
5 95,304 0.6806 64,864
NPV 121,005

An NPV of roughly 121,000 at an 8% discount rate. Positive, so the project beats putting the same money into the alternative the 8% represents.

Step 5: Read the Three Together

Measure Value What it says What it hides
ROI 58.9% The project returns more than it costs Timing; ignores the discount rate entirely
Break-even 2.69 years The sponsor waits under three years Everything after break-even, including a benefit collapse in year 4
NPV 121,005 Positive after accounting for the cost of money Sensitivity; one set of assumptions produces one number

Reported alone, each is easy to game. A project with a huge year-5 benefit looks good on ROI and bad on break-even. Report all three.

Step 6: Test the Assumptions

The NPV is a single point on a curve. Before approval, re-run it against pessimistic inputs. Here, with benefits flat instead of growing 10% a year:

Scenario NPV Break-even
Base case 121,005 2.69 years
Benefits flat at 90,000 55,830 3.29 years
Benefits flat, costs +20% 22,600 3.95 years
Benefits 25% below plan −18,700 never within 5 years

The project survives two of the three pessimistic cases and fails the third. That is the useful output: not "NPV is 121,005", but "this is worth doing unless benefits land more than about a fifth below plan, so measure realised benefits from year 1 and be ready to stop."

#

The base case NPV is 121,005 and total net cash flow is 203,690. Why is the NPV so much lower?

#

The sensitivity table shows a negative NPV when benefits land 25% below plan. What is the right conclusion for the feasibility study?