Defect Lifecycle

A defect report moves through a defined set of states from discovery to closure. The value of naming the states is that everyone knows who holds it, what has to happen next, and what "done" means for it.

stateDiagram-v2
    [*] --> New
    New --> Triaged: accepted, prioritised
    New --> Rejected: not a defect, duplicate, works as designed
    Triaged --> Assigned
    Assigned --> InProgress
    InProgress --> Fixed: change merged
    Fixed --> Verified: retested and confirmed
    Fixed --> Reopened: still reproducible
    Reopened --> Assigned
    Verified --> Closed
    Rejected --> [*]
    Closed --> [*]
    Triaged --> Deferred: real, not now
    Deferred --> Triaged: re-evaluated

What happens in each state

State Owner The question being answered
New Reporter What did you see, and how do we reproduce it?
Triaged Product plus engineering Is it real, how bad, when
Assigned Team Who is fixing it
In progress Developer What is the actual cause
Fixed Developer Change merged, plus a regression test
Verified Tester Reproduced on the old build, gone on the new one
Closed Tester or reporter Nothing outstanding
Reopened Tester Still reproducible, back to the team
Deferred Product Accepted risk with a review date
Rejected Triage Duplicate, not a defect, or intended behaviour

Triage

The step that keeps the process from becoming a queue nobody manages.

graph TD
    N[New defect] --> R{Reproducible?}
    R -->|no| INFO[Need more information from the reporter]
    R -->|yes| D{Duplicate?}
    D -->|yes| LINK[Link and close]
    D -->|no| S["Assign severity and priority"]
    S --> W{Fix now, next, or defer?}
    W --> ASSIGN[Assign, or place on the backlog with a decision recorded]

Triage should be regular and short. A backlog reviewed weekly stays a decision log. One reviewed twice a year becomes an archive nobody reads, and its size becomes an argument rather than information.

Severity and priority are set here, and they are two different things. See severity versus priority.

Rules that keep the lifecycle honest

  • The reporter closes, or a tester does. A developer marking their own fix as closed removes the verification step entirely.
  • Verify on the same steps as the report. Confirming an approximation of the scenario is how defects get reopened by users instead of testers.
  • Every fix leaves a regression test. Otherwise the defect can return silently. See regression testing.
  • Deferred means a date. A deferred defect without a review date is a closed defect wearing a disguise.
  • Reopened is data, not blame. A high reopen rate points at unclear reports, unverified fixes, or environments that differ.

What the data is for

The lifecycle produces the numbers that drive quality assurance rather than individual fixes:

Metric Signal
Escaped defects per release How much the process is leaking
Where defects are found Whether testing is shifting left
Time in each state Where the queue actually is, often triage rather than fixing
Reopen rate Fix quality and verification quality
Defect clustering by module Where to aim the next test effort

Check Your Understanding

#

Why should a developer not close their own defect after fixing it?

#

A high proportion of defects are reopened after being marked fixed. What does this most likely indicate?